Contract Awards

Contract Award Data: DCPL-2014-C-0006

Department: Capital ConstructionCOTR: Kim FullerAmount: $1,495,575.21Period: Base Year/4 One Year OptionsCaption: (7) Day Janitorial Services at 25 Neighborhood LibraryMore Information

Contract Award Data: DCPL-2013-C-0003A

Department: Capital ConstructionCOTR: Chris WrightAmount: $57,192.00Period: 120 days from Contractors signed NTPCaption: Design-Build Svcs (Woodridge Library Modular) Phase 1More Information

Contract Award Data: DCPL-2013-C-0002

Department: Capital ConstructionCOTR: Jeff BonvechioAmount: $146,800.00Period: 365 days from Contractors signed NTPCaption: Zoning and land use legal services (Woodridge Library)More Information

Contract Award Data: DCPL-2013-C-0001

Department: Capital Construction COTR: Chris Wright Amount: $107,274.00 Period: 365 days from Contractors signed NTP Caption: Old Benning Site Restoration ServicesMore Information

Contract Award Data: DCPL-2012-C-0008A

Department: Capital Construction COTR: Kim Fuller Amount: $52,000.00 Period: 365 days from Contractors signed NTP Caption: CM at Risk Services (Woodridge Library)More Information

Contract Award Data: DCPL-2012-C-0007

Department: Facilities Management COTR: Reginold Mitchell Amount: $492,817.00 Period: 11/2/12 – 9/30/13 (Base Year) Caption: 6 Day System-Wide Janitorial ServicesMore Information

Contract Number: DCPL-2012-C-0001

Department: Capital Construction COTR: Kim Fuller Amount: $1,485,710.00 Period: April 19, 2012 – 1,275 day from contractors signed NTP Caption: A/E Services (Woodridge Library)More Information

Contract Number: DCPL-2012-I-0002

Department: Facilities Management COTR: Edward Hampton Amount: $99,779.20 Period: 3/12/12 – 9/30/12 Caption: Landscape, Lawn and Snow Removal ServicesMore Information

Contract Number: DCPL-2011-C-0007

Department: 21st Century Capital Projects COTR: Chris Wright Amount: $839,500.00 Period: 181 Days from signed Notice To Proceed Caption: Design/Build Services –Northeast Neighborhood LibraryMore Information

Contract Number: DCPL-2011-C-0004A

(Phase 1 Pre-Construction)

Department: Capital Construction COTR: Kim Fuller Amount: $12,000.00 Period: 10/3/11 - 12/30/11 Caption: Interior Improvements to the Business Science and Technology Division & Great Hall at the Martin Luther King LibraryMore Information