Repairs to Southeast's Front Entrance Coming in August

In order to better serve the public, the front entrance of the Southeast Library will undergo repairs and upgrades this August. This work will consist of replacing the front door and installing security controls.  Work will take place between Thursday, August 14 and Monday, August 25. The preliminary work schedule is as follows:
 
Thursday, August 14 - Work will be performed from 6 a.m. to 12:30 p.m. The front entrance will be open to the public.
 
Friday, August 15 - Work will be performed from 6 to 9 a.m. The front entrance will be open to the public.
 
Tuesday, August 19 through Friday 22 – Work will be performed all day. The front entrance will be closed to the public. Traffic will be rerouted to the rear entrance facing D St, SE. This entrance is ADA compliant.
 
Friday, August 22 – Construction will be complete by the end of the workday.
 
Monday, August 25 – The new front entrance will ready to open for the public at 9:30 a.m.
 
We apologize for the inconvenience.